AgrolaAutarcoAxpoBEE EnergyCompanion EnergyDynamic Energy TradingDexterDNO Relay ControlEdmijEnergy Flexibility Solutions (EFS)EliaEnervalisEngiePlan-ahead APIEPEX Spot SolarEuropean CommoditiesFlowerFrank EnergieFuseboxGreenchoiceHallostroomImbyJoulenKratTradeNew integrationsNext EnergyOpinumParagraph 14a IntegrationPleeviRepoweredScholtTrevionVGT EnergyYuso - Battery ControlYuso - Solar Curtailment
SpecificationsStatus LEDsControl response timeVideo tutorialsCertificatesLicenseSafety, maintenance and legal notices
External Signals
Trevion logo

Setting up Trevion

The manual describes the steps to set up 'Trevion - Imbalance' on the SmartgridOne Controller.

Supported Devices

Device TypeVariantsSupported
Solar InvertersAll✅
Storage Devices❌
EV Chargers

Supported Countries

CountrySupported
Belgium✅
Netherlands❌

Prerequisites

1. Add the batteries

Login to the commissioning interface and make sure the devices are added to the SmartgridOne Controller.

2. Check the grid power limits

In the settings, the grid power limits should be set correctly. Click Settings and check the highlighted setting in the image. If necessary, adjust the settings.

3. Custom Fields

The following information must be known before adding the Control Signal:

  • Curtailment Threshold

    • The imbalance price threshold at which curtailment begins.
  • Curtailment Depth

    • The percentage of nominal inverter power to be curtailed during curtailment periods.
    • A value of 100 means 0% production during curtailment periods.
  • Curtailment Strategy

    • Limit the power of inverters (recommended).
    • Switch off a subset of inverters (less accurate; only necessary if inverters do not support setpoint control).
  • Timeout

    • If the connection with the servers is lost, this defines how long we continue using the last received value before reverting to local control.
  • Daily Overrides

    • The values above can be adjusted on specific days of the week (e.g., Sunday) if needed.
    • Use the format: weekday (integer); start time (hh:mm); duration in minutes (integer); threshold; curtailment depth.

Add 'Trevion - Imbalance'

Image 1
Image 1

In the next page, you have the option to include/exclude devices for remote control. Ensure to mark all checkboxes of devices you'd like to include.

Note

When using multiple batteries, they are aggregated into one (virtual) asset for Trevion.

Image 1

'Trevion' is now set up on the SmartgridOne Controller.